If you have ever had the pleasure of working with Microsoft Project you will likely be quite happy with it until you start changing the RESOURCE UNITS percentages (in the TASK INFORMATION pane). If you make changes you will find that it often miscalculates (or appears to miscalculate) the number of HOURS in WORK. After reading many many blogs and help files, I was about to give up on this when I found a reproducable process to have it calculate the number of days in DURATION correctly:
Click on these screen shots for details:
The three task types used in Project are:
Project uses fixed units by default.
Each of the task types affects scheduling when you edit one of the three elements as follows.
In a | If you revise units | If you revise duration | If you revise work |
---|---|---|---|
Fixed units task | Duration is recalculated. | Work is recalculated. | Duration is recalculated. |
Fixed work task | Duration is recalculated. | Units are recalculated. | Duration is recalculated. |
Fixed duration task | Work is recalculated. | Work is recalculated. | Units are recalculated. |
You may find the following links useful if you need more details
http://www.techrepublic.com/article/microsoft-project-tutorial-duration-and-task-types/1031576 and
http://office.microsoft.com/en-us/project-help/change-the-task-type-project-uses-to-calculate-task-duration-HP010092039.aspx
This website uses cookies.
View Comments
Your articles are extremely helpful to me. MS Project calculations are a hard to understand.
Bengkek
nothing is working with my problem.
i'm just calculating days (duration) from (start) 01.11.2013 to (finish) 30.12.2013. simply it should count 60 days in duration column but its calculating 42 days :/
i have tried changes in MS Project options but problem still exists :(
any solution please???
Kiran,
Duration does not count non-working days (weekends, holidays).
I have a MS Project problem: say you have 3 rooms and 5 clerks, they will work for 3 weeks, one clerk in each room daily , 5 days a week. How do you get that schedule done (which clerk works when) ?
I'm sorry, this is beyond my scope. :(
Had an activity that was not started with 2 days in the duration field and yet showed 5 days in the between the scheduled start and finish date. It made no sense as there were no resources involved, the predecessors were not driving out the finish date and the calendar did not have any non-working periods within the start and finish dates, apart from a sunday. Everything looked right and I experimented with all kinds of options. Finally, I started making random changes to one field after another, calcing after each one. That is when I hit pay-dirt. I changed the % complete from 0 to 1 and hit enter and the program finally calculated the activity correctly. I then changed the % complete back to zero and all was fine.
Has anyone experienced anything like that before?
I thought I'd be here all night trying to figure this out. Thank you so much. Completely saved me a night's sleep!
OMG! Thank you for adding your 2 cents on this. It totally helped me out. I had the exact same issue and it was highly annoying.
Thanks again!